In 1995, the High-Energy Piping Strategic Management Plan (HEPSMP) was initiated at TransAlta Utilities Corporation (TAU) for the three generating facilities. At that time, it was recognized that several of the piping systems were exhibiting signs of creep relaxation, with some hangers bottomed or topped out online and/or offline. Previous hanger adjustment attempts were not always adequate. The program workscope included: 1) hot and cold piping system walkdowns, 2) selection of high-priority girth weld inspection locations, 3) examination of critical weldments, 4) weld repairs where necessary, 5) adjustments or modifications of malfunctioning steam line hangers, and 6) recommended work for future scheduled outages. Prior to 1996, examination locations were limited to the traditional locations of the terminal points at the boiler and turbine, with reexaminations occurring at arbitrary intervals. Since the terminal points are not necessarily the most highly stressed welds causing service-related creep damage, service damage may not occur first at the pre-1996 examined locations. There was a need to maximize the safety and integrity of these lines by ensuring that the highest risk welds were identified and given the highest priority for examination. An engineering consulting company was selected to prioritize the highest risk weldments for each piping system. This risk-based methodology included the prediction and evaluation of actual sustained loads, thermal expansion loads, operating loads, multiaxial stresses, creep relaxation, and cumulative creep life exhaustion. The technical process included detailed piping system walkdowns and application of advanced analytical techniques to predict and rank creep/fatigue damage for each piping system. TAU has concluded that the program has met its objective of successfully prioritizing inspection locations. The approach has also resulted in reducing the scope and cost of reexaminations. Phases 1 and 2 evaluations and examinations have been completed for all units. Results of some of the important aspects of this program are provided as case history studies.
Skip Nav Destination
Article navigation
February 2001
Technical Papers
The TransAlta High-Energy Piping Program—A Five-Year History
Marvin J. Cohn,, Manager, Piping System Life Management
Marvin J. Cohn,, Manager, Piping System Life Management
Aptech Engineering Services, Inc., Sunnyvale, CA 94089
Search for other works by this author on:
Marvin J. Cohn,, Manager, Piping System Life Management
Aptech Engineering Services, Inc., Sunnyvale, CA 94089
Contributed by the Pressure Vessels and Piping Division and presented at the Pressure Vessels and Piping Conference, Seattle, Washington, July 23–27, 2000, of THE AMERICAN SOCIETY OF MECHANICAL ENGINEERS. Manuscript received by the PVP Division, January 2000; revised manuscript received October 23, 2000. Editor: S. Y. Zamrik.
J. Pressure Vessel Technol. Feb 2001, 123(1): 65-69 (5 pages)
Published Online: October 23, 2000
Article history
Received:
January 1, 2000
Revised:
October 23, 2000
Citation
Cohn, , M. J. (October 23, 2000). "The TransAlta High-Energy Piping Program—A Five-Year History ." ASME. J. Pressure Vessel Technol. February 2001; 123(1): 65–69. https://doi.org/10.1115/1.1344236
Download citation file:
Get Email Alerts
Cited By
The Behavior of Elbow Elements at Pure Bending Applications Compared to Beam and Shell Element Models
J. Pressure Vessel Technol (February 2025)
Related Articles
Life Management of High-Temperature Piping and Tubing in Fossil Power Plants
J. Pressure Vessel Technol (August,2000)
Welding Residual Stresses and Effects on Fracture in Pressure Vessel and Piping Components: A Millennium Review and Beyond
J. Pressure Vessel Technol (August,2000)
Failure Mechanisms of High Temperature Components in Power Plants
J. Eng. Mater. Technol (July,2000)
Creep Crack Growth in X20CrMoV 12 1 Steel and Its Weld Joint
J. Pressure Vessel Technol (May,2001)
Related Proceedings Papers
Related Chapters
Section XI Flaw Acceptance Criteria and Evaluation Using Code Procedures
Online Companion Guide to the ASME Boiler & Pressure Vessel Codes
Defect Assessment
Pipeline Integrity Assurance: A Practical Approach
Basic Concepts
Design & Analysis of ASME Boiler and Pressure Vessel Components in the Creep Range